A Photo History of the Barn

 

The VYCC Education and Training Center as it stands today. Let us take you on a brief photo history to understand the process and work that has gone into restoring this historic piece of Vermont.


The West Monitor Barn as it appeared in the early 1900s

By 1995 the West Monitor Barn was falling into disrepair, in part due to a leaky roof.

Dismantling of the West Monitor Barn began during the late fall of 2000.

During the winter of 2001 hemlock logs were cut on nearby property to provide wood for the new barn timbers.

A portable sawmill was brought on site to mill the replacement timbers for the new barn.

The new timbers were cut and stacked near the East Monitor Barn, a companion barn also built in the early 1900s.

Crew members from the Vermont Youth Conservation Corps helps with the construction of the new barn foundation during the summer of 2001.

The completed foundation.

Each timber for the new barn was cut and labeled, ready to be put in place as the frame is erected.

Traditional methods are used to construct the new frame, including pegs which hold the floor joists in place.

A crew from Restoration and Traditional Building erects the new barn frame during the summer of 2002.

Vermont Youth Conservation Corps crew members use stones from the original barn to complete the new foundation.

Vermont Youth Conservation Corps crews and volunteers along with professional contractors worked to lay and sheath the first floor.

In July of 2003 the Vermont Youth Conservation Corps and the Richmond Land trust held an open house for interested parties and supporters. Here we see the cornerstone placement by Governor Douglas with help from a Community Crew.

During the fall and winter of 2003 the second story framing was completed by Lewandoski Restoration using original and new timbers.

The frame was erected with historical accurate building techniques, using wooden pegs to join and secure the timbers.

 
In December of 2003 the "high drive" beams were placed with the assistance of a crane.
Throughout the early spring
and summer of 2004 Robert Reap and crew
sheathed the second floor.

May 15th, 2004 saw the placement of the reconstructed monitor.

By the end of May the remaining roofing and sheathing was completed.

The hand built cupola was raised on August 19th with 200 supporters in attendance.

Throughout the end of summer and through the fall Reap Construction worked to complete the monumental task of installing the red clapboard siding to the exterior.

The pine clapboard was installed in November and the barn was restored to its original glory.

In December and January we broke ground on the carriage barn and the foundation was poured.
Throughout the cold months of January and February Reap Construction worked tirelessly to erect the frame and sheath the carriage barn.